Menu

Walnut Elementary Construction

Building For The Future

Walnut Elementary Upgrades

This project will build a new storm shelter gym and four new classrooms. Existing classrooms will be renovated. The front office will be expanded for the necessary student support spaces and include a new more secure building entry. The kitchen will be expanded, and the current gym/cafeteria will become a cafeteria and multipurpose space. Work will upgrade building mechanical and electrical systems.

Project Update: 12/17/2020

Slab on grade placement for the classrooms took place last week. Crews started laying up CMU block this week and in-wall rough-in has started. Steel erection will follow CMU walls.

Pete Smith
Project Superintendent – McCownGordon Construction

Project Update: 12/04/2020

Plumbing underground rough-in is complete in the classroom areas. Slab prep has started and electrical underground will be going at the same time. Next week we will bore the sanitary line from the new addition to Grove Ave. We look to make a slab placement next week as long as the weather holds. Masonry walls will follow.

Pete Smith
Project Superintendent – McCownGordon Construction

Project Update: 11/20/2020

Concrete footings and foundation walls have been placed. Crews backfilled foundation walls this week and plumbing underground has started which will be followed by electrical underground. We are looking at placing the 1st slab on grade after Thanksgiving Break.

Pete Smith
Project Superintendent – McCownGordon Construction

Project Update: 11/6/2020

Crews are currently digging footings and tying reinforcing steel. Footings are scheduled to pour this week, followed by foundation wall placement early next week. After foundation walls are placed, we will backfill them and start plumbing underground.

Pete Smith
Project Superintendent – McCownGordon Construction

Project Update: 10/23/2020

 

The majority of the building pad is complete. Crews started footings this week and foundation wall installation will start next week.

 

Pete Smith
Project Superintendent – McCownGordon Construction

Project Update: 10/9/2020

 

Walnut Elementary is off to a good start. We had a Groundbreaking Ceremony last week with USD 253, HTK Architects, and McCownGordon Construction. Currently, site demo is complete and Landworx is constructing the building pad for the new South Addition. Footings are scheduled to start late this month.

Pete Smith
Project Superintendent – McCownGordon Construction

USD253

Pin It on Pinterest