Early Learning Center Construction
Building For The FutureEarly Learning Center Construction
Maynard will be replaced with a new state of the art early childhood facility built near Riverside Elementary. The new center will be specifically designed to serve the needs of young children in the district through play-based learning to grow social skills, coordination, and empowered learners. The facility will have expanded classrooms and learning environments, student support spaces, and indoor activity areas. Outdoor playgrounds will feature age-appropriate areas for play and exploration.
Project Update: 1/15/2021
We have been working hard at getting the footings in and some of the mechanical underground, the weather has not been cooperating with us much until this week. We are hoping to have the building footings completed by mid-next week and start focusing on the slab on grade. We are scheduled to have our first flat pour (Area B) on February 2nd.
EDWARD WITT, STSC
Project Superintendent – McCownGordon Construction



Project Update: 12/11/2020
Work on underground utilities has begun, the building pad is complete, and is ready to start footings and foundations. Concrete crews will start this work beginning next week. The site work is coming along nicely, most of the parking lots are to sub-grade and a lot of this site work should be completed in the next couple of weeks.
EDWARD WITT, STSC
Project Superintendent – McCownGordon Construction